1. The installation must conform to the requirements
of the authority having jurisdiction or, in the absence
of such requirements, to the latest revision of the
National Fuel Gas Code, ANSI Z223. (Available from
the American Gas Association, 8501 E. Pleasant
Valley Road, Cleveland, Ohio 44134). Reference
should also be made to local gas utility regulations
and other codes in effect in the area in which the
installation is to be made. When installed in Canada:
The latest revision of the CAN 1-B 149.1 and/or B 149.2
Installation Codes for Gas-Burning Equipment and/or
local codes.
2. Where required bythe authority having jurisdiction,
the installation must conform to American Society
of Mechanical Engineers Safety Code for Controls
and Safety Devices ForAutomaticatly Fired Boilers,
ANSI/ASME No.CSD-1.
3. This boiler series is classified as a Category 1 and
the vent installation shall be in accordance with Part
7 of the National Fuel Gas Code noted above when
installed in the United States. In Canada refer to
the CAN1-B149.1 and or B149.2 Installation Codes
for Gas-Burning Equipment. Also refer to applicable
provisions of the local building codes.
4. This boiler has met safe lighting and other
performance criteria with the gas manifold and control
assembly on the boiler per the latest revision of ANSI
Z21.13/CGA 4.9.
5. The boiler shall be installed such that the gas
ignition system components are protected from
water(dripping, spraying, rain, etc.)during appliance
operation and service, (circulator replacement,
condensate trap, control replacement, etc.).
6. Locate boiler on level, solid base as near the
chimney as possible and centrally located with respect
to the heat distribution system as practical.
7. Allow 24 inches at the front and right side for
servicing and cleaning.
8. When installed in a utility room, the door shoutd be
wide enough to allow the largest boiler part to enter,
or to permit replacement of another appliance such
as a water heater.
9. FOR INSTALLATION ON NON-COMBUSTIBLE
FLOORS ONLY - For installation on combustible
flooring special base part no. 325-2-8.00 must be
used. The boiler can not be installed on carpeting.
Minimum clearances to combustible construction
are:
TOP ................................................... 18 IN.
FRONT ...................................... ALCOVE *
FLUE CONNECTOR ........................... 6 IN.
REAR ................................................... 8 IN.
CONTROL SIDE .................................. 9 IN.
OTHER SIDE ....................................... 3 IN.
NOTE: Greater clearances for access should
supersede fire protection clearances.
* The definition of an Alcove is a three sided space with
no wall in front of the boiler. TheANSI standard for an
alcove is 18 inches from the front of an appliance to
the leading edge of the side walls as shown below.
MINIMUM CLEARANCES TO COMBUSTIBLE CON-
STRUCTION (AS SEEN FROM ABOVE)
_ 9"_ 3"
18"
1
Seitenansicht 3
1 2 3 4 5 6 7 8 9 ... 25 26

Kommentare zu diesen Handbüchern

Keine Kommentare